Technological map for floor insulation with foam. Ttk

Technological map for the Penoplex insulation device

Application area technological map on penoplex

The technical map was developed for a roof with a slope of less than 10% in relation to a one-story shop industrial building, the overall scheme of which is 72x24 m.

The composition of the work under consideration includes the laying of insulation boards on bitumen.

Organization and technology of the construction process

Before starting work on the thermal insulation device, the work on laying the profiled sheet must be completed.

For the device of thermal insulation, extruded polystyrene foam material "Penoplex" is used, laid on bitumen BN-90/10 GOST 6617-76. Plates Penoplex are certified in the systems of GOST R of the State Standard of Russia and Mosstroycertification and are approved for use as a heat and sound insulating material by the Sanitary and Epidemiological Conclusion of the Center for Sanitary and Epidemiological Supervision.

Plates "Penoplex" are delivered to the site to the mast lift. The supply of insulation boards to the roof is carried out by a mast cargo lift C-598A. The plates are transferred to the workplace manually.

Hot bitumen is prepared centrally and delivered to the construction site in asphalt distributors. The supply of bitumen to the coating is carried out by the SO-100A machine. The SO-100A machine is mounted on a trailer. The bitumen from the asphalt distributor is pumped into the SO-100A machine and fed through the pipeline to the coating. The pipeline on the vertical section is attached to the wall of the building with brackets with clamps, and on the inventory racks with a reverse slope of 0.01%.

Bitumen is delivered to the place of work in tanks filled to 3/4 of the volume, on a pneumatic wheeled trolley. The tank is filled from the dispensing points of the bitumen pipeline.

Slab heat-insulating foam boards are laid on the coating on bitumen with a snug fit to the vapor barrier layer.

Before starting work, the roofer checks the dryness of the base and installs beacons that allow the slabs to be laid in an even layer. For the production of works, the coating in the plan is divided into grips (9x12).

All work on the installation of Penoplex plates is carried out to meet the supply of materials. Before laying the slabs, hot bitumen (160-190) is applied to the surface of the coating in strips 100-120 mm wide every 150-200 mm. Bitumen is poured into buckets and leveled over the surface with brushes.

Thermal insulation boards must be laid from the top marks to the bottom, with the long side across the roof slope.

The joints of the slabs have a stepped shape, which provides a tight lock and allows you to lay the slabs with an overlap.

Grease the ends of the plates located at the edges of the coating with bitumen.

When storing and transporting thermal insulation boards, measures must be taken: the boards can be stored outdoors in their original packaging, but they must be protected from prolonged exposure to sunlight to prevent destruction of the top layer of the boards.

After performing thermal insulation during the day, it is necessary to cover the slabs with geotextile material, which will protect the slabs from ultraviolet sunlight, followed by covering it with gravel 5 cm thick.

Thermal insulation device winter period in accordance with SNiP III-20-74*, it is allowed at an outside air temperature of at least -20 ° С.

It is forbidden to lay the slabs on surfaces that have not been cleared of frost, snow and ice.

To protect the bases from damage when moving people, a wooden flooring is arranged on the surface.

Calculation Nº1: the number of lifts of insulation boards "Penoplex" mast lift:

The size of the Penoplex plates is 2250x1500x30 mm;

Consumption of plates "Penoplex" - (72x24) / (2.25x1.5) = 512 pcs;

The lift lifts 29 plates;

Number of lifts 512/29=18.

Calculation Nº2: Norm of time for bitumen supply using the SO-100A machine:

Meter - 1 m³ of bitumen;

The amount of bitumen per coating is 2 tons or 1.82 m³;

Machine productivity - 6 m³;

The composition of the link: driver 3 rubles - 1 person, thermal insulator 2 rubles - 1 person.

Norm of time for the meter: man-hour.

The walls of houses built of bricks, various wall blocks, and even more so - representing a reinforced concrete structure, in most cases do not meet the requirements for regulatory thermal insulation. In a word, such houses need additional insulation to prevent significant heat loss through the building envelope.

There are many different approaches to . But if the owners prefer the exterior finish of their house, made of decorative plaster, in a “pure” form or with the use of facade paints, then the best choice is the wet facade insulation technology. In this publication, it will be considered how difficult such work is, what is required to carry it out, and how all this can be done on our own.

What is meant by "wet facade" insulation system?

First of all, it is necessary to understand the terminology - what is the “wet facade” technology, and how does it differ from, say, ordinary wall cladding with insulating materials with further decorative sheathing with wall panels (siding, block house, etc.)


The clue lies in the name itself - all stages of work are carried out using building compounds and solutions that are diluted with water. The final stage is the plastering of already insulated walls, so that the thermally insulated walls become completely indistinguishable from ordinary, covered decorative plaster. As a result, two most important tasks are solved at once - ensuring reliable insulation of wall structures and high-quality facade design.

An approximate scheme of insulation using the "wet facade" technology is shown in the figure:


Schematic diagram of insulation using the "wet facade" technology

1 - insulated facade wall of the building.

2 - a layer of building adhesive mixture.

3 - insulation boards of synthetic (of one type or another) or mineral (basalt wool) origin.

4 - additional mechanical fastening of the thermal insulation layer - dowel-"fungus".

5 - protective and leveling plaster layer, mesh reinforced(pos. 6).

Such a system of complete thermal insulation and facade finishing has a number of significant advantages:

  • It does not require a very material-intensive installation of a frame structure.
  • The system is quite easy. And it can be successfully used on most facade walls.
  • The frameless system predetermines and practically complete absence"cold bridges" - the insulation layer is monolithic over the entire surface of the facade.
  • Facade walls receive, in addition to insulation, an excellent soundproof barrier, which helps to reduce both airborne and impact noise.
  • With the correct calculation of the insulation layer, the “dew point” is completely removed from the wall structure and taken out. It excludes the possibility of wetting the wall and the appearance of colonies of mold or fungus in it.
  • The outer plaster layer is characterized by good resistance to mechanical stress, to atmospheric action.
  • In principle, the technology is simple, and with strict adherence to the rules, any homeowner can handle it.

  • With high-quality performance of work, such an insulated facade will not require repairs for at least 20 years. However, if there is a desire to update the finish, then this can be easily done without violating the integrity of the thermal insulation structure.

The disadvantages of this method of insulation include:

  • Seasonality of work - they can only be carried out at positive (at least + 5 ° C) temperatures, and in stable good weather. It is undesirable to carry out work in windy weather, at too high (over + 30 ° C) air temperatures, on the sunny side without providing protection from direct rays.
  • Increased demands on the high quality of materials, and on the exact observance of technological recommendations. Violation of the rules makes the system very vulnerable to cracking or even detachment of large fragments of insulation and trim.

As a heater, as already mentioned, mineral wool or expanded polystyrene can be used. Both materials have their advantages and disadvantages, but still, for a “wet facade”, high-quality mineral wool looks preferable. With approximately equal values ​​​​of thermal conductivity, mineral wool has a significant advantage - vapor permeability. Excess free moisture will find its way out of the premises through the wall structure and evaporate into the atmosphere. It is more difficult with expanded polystyrene - its vapor permeability is low, and in some types it generally tends to zero. Thus, the accumulation of moisture between the wall material and the insulation layer is not excluded. This is not good in itself, but at abnormally low winter temperatures, cracking and even “shooting off” of large areas of insulation along with finishing layers occur.

There are special topics for expanded polystyrene - with a perforated structure, in which this issue is resolved to a certain extent. But basalt wool has another important advantage - absolute incombustibility, which polystyrene foam cannot boast of in any way. And for facade walls, this is a serious issue. And this article will consider best option– “wet facade” insulation technology using mineral wool.

How to choose a heater?

Which mineral wool is suitable for a "wet facade"?

As is already clear from circuit diagram"wet facade", the insulation must, on one side, be mounted on an adhesive solution, and on the other, it must withstand a considerable load of the plaster layer. Thus, thermal insulation boards must meet certain requirements in terms of density, in terms of the ability to withstand loads - both for crushing (compression) and for breaking their fiber structure (stratification).

Naturally, not any insulation that belongs to the category of mineral wool is suitable for these purposes. Glass wool and slag wool are completely excluded. Only slabs of basalt fibers produced using a special technology are applicable - with increased rigidity and density of the material.

Leading manufacturers of insulation based on basalt fibers in their product line provide for the production of plates specially designed for thermal insulation of walls with subsequent finishing with plaster, that is, for a “wet facade”. The characteristics of several of the most popular types are shown in the table below:

Name of parameters"ROCKWOOL FACADE BATTS""Baswool Facade""Izovol F-120""TechnoNIKOL Technofas"
Illustration
Material density, kg/m³ 130 135-175 120 136-159
Tensile strength, kPa, not less than
- for compression at 10% deformation45 45 42 45
- for stratification15 15 17 15
Thermal conductivity coefficient (W/m×°С):
- calculated at t = 10 °C0,037 0,038 0,034 0,037
- calculated at t = 25 °С0,039 0,040 0,036 0,038
- operational under conditions "A"0,040 0,045 0,038 0,040
- operational under conditions "B"0,042 0,048 0,040 0,042
Flammability group NGNGNGNG
Fire safety class KM0- - -
Vapor permeability (mg/(m×h×Pa), not less than 0,3 0,31 0,3 0,3
Moisture absorption by volume at partial immersion no more than 1%no more than 1%no more than 1%no more than 1%
Plate dimensions, mm
- lenght and width1000×6001200×6001000×6001000×500
1200×600
- plate thickness25, 30 to 180from 40 to 160from 40 to 200from 40 to 150

Experimenting with lighter and cheaper types of basalt wool is not worth it, since such a “wet facade” will probably not last long.

How to determine the required thickness of insulation?

As can be seen from the table, manufacturers offer a wide range of insulation thicknesses for the "wet facade", from 25 to 200 mm, usually in 10 mm increments.


What thickness to choose? This is by no means an idle question, since the “wet facade” system being created should provide high-quality thermal insulation of the walls. At the same time, excessive thickness is an extra cost, and in addition, excessive insulation can even be harmful in terms of maintaining an optimal temperature and humidity balance.

Usually, specialists calculate the optimal thickness of insulation. But it is quite possible to do this yourself, using the calculation algorithm presented below.

So, the insulated wall must have a total resistance to heat transfer not lower than the standard value determined for the given region. This parameter is tabular, it is in reference books, known in local construction companies, and in addition, for convenience, you can use the map-diagram below.


A wall is a multilayer structure, each layer of which has its own thermophysical characteristics. If the thickness and material of each layer, already existing or planned (the wall itself, internal and exterior finish etc.), then it is easy to calculate their total resistance, compare with the normative value in order to get the difference that needs to be “covered” by additional thermal insulation.

It will not bore the reader with formulas, but we will immediately suggest using a calculation calculator that will quickly and with a minimum error calculate the required thickness of insulation with basalt wool intended for facade work.

Calculator for calculating the thickness of the insulation of the "wet facade" system

The calculation is carried out in the following sequence:

  • Determine the normalized value of heat transfer resistance for walls from the map-scheme for your region (purple numbers).
  • Specify the material of the wall itself and its thickness.
  • Decide on the thickness and material interior decoration walls.

The thickness of the external plaster finish of the walls is already taken into account in the calculator, and it will not be required to make it.

  • Enter the requested values ​​and get the result. It can be rounded up to the standard thickness of manufactured insulation boards.

If a negative value is suddenly obtained, wall insulation is not required.

TYPICAL TECHNOLOGICAL CHART (TTK)

THERMAL INSULATION OF THE FACADE OF THE BUILDING WITH MINERAL COTTON PLATES "ROCKWOOL FACADE BUTTS D"

I. SCOPE

I. SCOPE

1.1. A typical technological map (hereinafter referred to as TTK) is a comprehensive organizational and technological document developed on the basis of methods scientific organization labor to perform the technological process and determining the composition of production operations using the most modern means mechanization and methods of performing work according to a specific technology. TTK is intended for use in the development of the Project for the Production of Works (PPR) by construction departments and is its integral part in accordance with MDS 12-81.2007.

Fig.1. Wall insulation scheme

1 - insulated Brick wall; 2 - insulation plate; 3 - dowel plate type; 4 - base plaster layer; 5 - reinforcing fiberglass mesh; 6 - primer layer; 7 - finishing plaster; 8 - base rail with special dowels


1.2. This TTC provides instructions on the organization and technology of work on the thermal insulation of the facade of the building of the MVP "ROCKWOOL FACADE BATTS D", determines the composition of production operations, requirements for quality control and acceptance of work, planned labor intensity of work, labor, production and material resources, measures for industrial safety and labor protection.

1.3. The regulatory framework for the development of technological maps are:

- standard drawings;

- building codes and regulations (SNiP, SN, SP);

- factory instructions and specifications (TU);

- norms and prices for construction - installation work s (GESN-2001 ENiR);

- production norms for the consumption of materials (NPRM);

- local progressive norms and prices, labor costs norms, material and technical resources consumption norms.

1.4. The purpose of the creation of the TC is to describe the solutions for the organization and technology of work on the thermal insulation of the facade of the building of the MVP "ROCKWOOL FACADE BATTS D", time in order to ensure their high quality, as well as:

- cost reduction of works;

- reduction of construction time;

- ensuring the safety of work performed;

- organization of rhythmic work;

- rational use of labor resources and machines;

- unification of technological solutions.

1.5. On the basis of the TTC, as part of the WEP (as mandatory components of the Work Execution Project), Working Flow Charts (RTC) are developed for the implementation certain types works on thermal insulation of the facade of the MVP "ROCKWOOL FACADE BATTS D" building.

The design features of their implementation are decided in each case by the Working Design. The composition and level of detail of materials developed in the RTK are established by the relevant contracting construction organization, based on the specifics and scope of work performed.

RTK are considered and approved as part of the PPR by the head of the General Contractor Construction Organization.

1.6. TTK can be tied to a specific object and construction conditions. This process consists in clarifying the scope of work, means of mechanization, the need for labor and material and technical resources.

The procedure for linking the TTK to local conditions:

- consideration of map materials and selection of the desired option;

- verification of the compliance of the initial data (volumes of work, time standards, brands and types of mechanisms, building materials used, composition of the worker link) to the accepted option;

- adjustment of the scope of work in accordance with the chosen option for the production of work and a specific design solution;

- recalculation of costing, technical and economic indicators, the need for machines, mechanisms, tools and material and technical resources in relation to the chosen option;

- design of the graphic part with a specific binding of mechanisms, equipment and fixtures in accordance with their actual dimensions.

1.7. A typical flow chart has been developed for engineering and technical workers (foremen, foremen, foremen) and workers performing work in the III temperature zone, in order to familiarize (train) them with the rules for performing work on the thermal insulation of the facade of the MVP "ROCKWOOL FACADE BATTS D" building ", using the most modern means of mechanization, progressive designs and materials, methods of performing work.

The technological map has been developed for the following scopes of work:

II. GENERAL PROVISIONS

2.1. The technological map was developed for a set of works on thermal insulation of the facade of the IVP building "ROCKWOOL FACADE BATTS D".

2.2. Works on thermal insulation of the facade of the building of the MVP "ROCKWOOL FACADE BATTS D" are carried out in one shift, the working hours during the shift are:

Where - the duration of the work shift without a lunch break;

Coefficient of output reduction;

- conversion factor.

In calculating the norms of time and duration of work, a one-shift mode of operation was adopted with a working shift of 10 hours with a five-day working week. The net working time during the shift is taken, taking into account the coefficient of output reduction due to the increase in the duration of the shift compared to the 8-hour working shift, equal to 0,05 and conversion factor 1,25 total time for a 5-day working week ("Methodological recommendations for the organization of the rotational method of work in construction, M-2007").

where - preparatory and final time, 0.24 hours, incl.

Breaks related to the organization and technology of the process include the following breaks:

Getting the job at the beginning of the shift and handing over the work at the end 10 min=0.16 hour.

Preparation of the workplace, tools, etc. 5 min=0.08 hour.

2.3. The scope of work performed during the thermal insulation of the facade of the building of the MVP "ROCKWOOL FACADE BATTS D" includes:

- geodetic marking of the facade of the building;

- preparation of the building base;

- priming the base of the facade with an adhesive primer;

- installation of a basement ebb;

- installation of ebb window block;

- installation of external side frames of the window unit;

- installation of a socle profile for installation of a heater;

- gluing heat-insulating plates to the base of the facade;

- mechanical fastening of heat-insulating plates to the facade;

- installation of reinforcing elements and profiles;

- creation of a protective reinforced plaster layer;

- anti-vandal protection measures;

- priming of the protective reinforced layer;

- application of a protective and decorative layer of facade plaster;

- priming of the decorative layer;

- Painting walls and slopes of the facade with acrylic paint.

2.4. For thermal insulation of the facade of the building, the following materials are used as the main materials: cement-lime mortar С22 (СЦС) according to GOST 7473-2010; deep penetrating primer "Weber.Рrim Contact"; adhesive composition "Weber.therm S 100"; reinforcing fiberglass mesh alkali-resistant (cell 5x5, 160 g/m); mineral wool boards ROCKWOOL Facade Butts D (size 1200x500x150 mm); primer acrylic tinting Weber.Pas UNI; silicate-silicone plaster Weber.Pas Extra Clean; acrylic paint facade Weber.Ton Akrylat; acrylic frost-resistant sealant MAKROFLEX FA131; sloping metal panels; aluminum plinth profile AL-150 (150x0.8x2500 mm); polyurethane foam MAKROFLEX; plate-type polymer anchor with a drive-in element (8/60x165 mm); PVC corner (20x20 mm) with fiberglass mesh (100x150 mm); PVC corner with dripper MAT D/05; PVC corner adjoining window, self-adhesive with reinforcing fiberglass mesh.

2.5. The technological map provides for the performance of work by an integrated mechanized unit consisting of: perforator RH2551 "STURM" (weight 2.8 kg, power 500 W, drilling 20 mm); drill driver Metabo Se 2800 (power 400 W); forced mortar mixer SO-46B (power 1.5 kW, loading volume 80 l); electric hand mixer ZMR-1350E-2 (weight 6.3 kg, power 1.35 kW); membrane spray gun electric Wagner DP-6830 (weight 30 kg, power 1.5 kW); Vacuum cleaner Karcher NT 14/1 And diesel power plant Atlas Copco QAS 125 (maximum power 111 kW) as a driving mechanism.

Fig.2. Diesel power station Atlas Copco QAS 125

Fig.3. Airbrush Wagner DP-6830

Fig.4. Mortar mixer SO-46B

Fig.5. Perforator RH2551 "STURM"

Fig.6. Drill driver Metabo Se 2800

Fig.7. Hand mixer ZMR-1350E-2

Fig.8. Vacuum cleaner Karcher NT 14/1


2.6. Work on the installation of an insulated facade should be carried out, guided by the requirements of the following regulatory documents:

- SP 48.13330.2011. "SNiP 12-01-2004 Organization of construction. Updated edition";

- SNiP 3.01.03-84. Geodetic works in construction;

- Manual to SNiP 3.01.03-84. Production of geodetic works in construction;

- SNiP 3.03.01-87. Bearing and enclosing structures;

- SNiP 3.04.01-87. Insulating and finishing coatings;

- SNiP 3.04.03-85. Protection building structures from corrosion;

- STO NOSTROY 2.33.14-2011. Organization of construction production. General provisions;

- STO NOSTROY 2.33.51-2011. Organization of construction production. Preparation and production of construction and installation works;

- STO NOSTROY 2.14.7-2011. Facade heat-insulating composite systems with external plaster layers. Rules for the production of works. Requirements for the results and the system for monitoring the work performed;

- SNiP 12-03-2001. Labor safety in construction. Part 1. General requirements;

- SNiP 12-04-2002. Labor safety in construction. Part 2. Construction production;

- PB 10-14-92*. Rules for the construction and safe operation of cranes;
________________
* PB 10-14-92 are not valid. Instead, the Federal norms and rules in the field of industrial safety of November 12, 2013 N 533 apply hereinafter. - Database manufacturer's note.

- VSN 274-88. Safety regulations for the operation of self-propelled jib cranes;

- RD 11-02-2006. Requirements for the composition and procedure for maintaining executive documentation during construction, reconstruction, overhaul capital construction facilities and requirements for certificates of survey of works, structures, sections of engineering and technical support networks;

- RD 11-05-2007. The procedure for maintaining a general and (or) special journal for recording the performance of work during construction, reconstruction, overhaul of capital construction projects.

III. ORGANIZATION AND TECHNOLOGY OF WORK PERFORMANCE

3.1. In accordance with SP 48.13330.2001 "SNiP 12-01-2004. Organization of construction. Updated edition" prior to the commencement of construction and installation works at the facility, the Contractor is obliged to obtain from the Customer, in the prescribed manner, project documentation and permission to perform construction and installation works. Work without permission is prohibited.

3.2. Prior to the start of work on the installation of thermal insulation of the facade of the building, it is necessary to carry out a set of organizational and technical measures, including:

- develop RTK or PPR for thermal insulation of the facade of the building;

- appoint persons responsible for the safe performance of work, as well as their control and quality of performance;

- briefing the members of the safety team;

- establish temporary inventory household premises for storing building materials, tools, inventory, heating workers, eating, drying and storing work clothes, bathrooms, etc.;

- provide the site with working documentation approved for the production of work;

- prepare machines, mechanisms and equipment for the production of work and deliver them to the facility;

- provide workers with manual machines, tools and personal protective equipment;

- provide the construction site with fire-fighting equipment and signaling equipment;

- prepare places for storing building materials, products and structures;

- fence the construction site and put up warning signs illuminated at night;

- provide communication for operational and dispatching control of the production of works;

- deliver to the work area necessary materials, fixtures, inventory, tools and means for the safe production of work;

- check quality certificates, passports for reinforcing steel, lumber, plywood;

- to test construction machines, means of mechanization of work and equipment according to the nomenclature provided for by the RTK or PPR;

- draw up an act of readiness of the object for the production of work;

- obtain permission from the technical supervision of the Customer to start work (clause 4.1.3.2 of RD 08-296-99*).
________________
* RD 08-296-99 is not valid. - Database manufacturer's note.


3.4. Prior to the start of work on the installation of insulation of the facade of the building, the provisions of the TTC must be completed preparatory work, including:

- accepted from the customer facade for finishing;

- roofing, cornice overhangs and canopies over the entrances were installed;

- installation of window and door blocks is completed;

- completed work on the installation of all floor structures, balconies and loggias;

- installed, tested for strength and accepted by the commission scaffolding mounted facade lift;

- around the building the blind area is made;

- installed all the fastenings of drainpipes and fire escapes;

- Passages for pedestrians are fenced.

3.4.1. For the installation of insulation, the facade of the building is transferred by the General Contractor / Customer to the Subcontractor Construction Organization, according to the Acceptance and Transfer Certificate of the facade for finishing, in accordance with Appendix A, STO NOSTROY 2.14.7-2011.

3.4.2. The technology of work on the installation of roofing, window and door blocks, the performance of internal finishing works are considered in separate technological maps.

3.4.3. Geodetic marking of the facade of the building (vertical and horizontal axes under the structure) is carried out by a link of surveyors in the following sequence:

- checking the geometric parameters of buildings for compliance with their design values;

- drawing up a three-dimensional digital model of facades in the 3D AutoCAD environment;

- marking of horizontal and vertical axes of fastening of facade cladding structures;

- drawing up an executive drawing on the vertical planes of the building;

- drawing markup marks on the drawing of the facade of the building.

3.4.4. The work performed must be presented to the representative of the Customer's technical supervision for inspection and documentation by signing the Certificate of breakdown of the axes of the capital construction object on the ground in accordance with Appendix 2, RD 11-02-2006 and obtain permission to work on the installation of facade wall insulation.

3.4.5. The act of laying out the axes must be accompanied by an Executive scheme for setting out (laying out) the horizontal and vertical axes of fastening of the facade cladding structures in the accepted system of coordinates and heights.

3.4.6. The completion of the preparatory work is recorded in the General Work Log (The recommended form is given in RD 11-05-2007) and must be accepted according to the Act on the implementation of labor safety measures, drawn up in accordance with Appendix I, SNiP 12-03-2001.

3.5. Preparation of the building base

3.5.1. Surfaces before cladding must be cleaned of mortar, dirt and concrete, the plinth - from construction debris. Separate irregularities of more than 15 mm, as well as general deviations of the surface to be lined from the vertical of more than 15 mm, must be corrected by cutting down the bulges on the surface and applying a leveling layer of cement mortar, which is applied without smoothing and grouting. At the end of the leveling, the surfaces are checked for the building level, plumb line and rule. All cracks are cut and rubbed with cement-sand mortar.

3.5.2. Next, mechanized cleaning of wall surfaces contaminated with lubricants, oils and anti-adhesive agents is carried out using water, with the addition of detergents using industrial vacuum cleaner for dry and wet cleaning Karcher NT14/1 Eco Te Advanced.

3.5.3. The marking of the surface of the facade of the building is carried out in the following sequence:

- the verticality of the wall is checked with a plumb line along the flat part after 2-3 m, as well as at the break points of the facade;

- the position of the horizontal seams of the cladding is marked with paint along the cord or slats are installed - orders;

- the outer surface of the cladding is marked with a horizontal cord at the height of its first row;

- after hanging the wall, it is marked out for making holes for anchors.

3.5.4. Drilling holes with a diameter of 8 mm for dowels using a manual perforator RH2551 "STURM" . Holes are cleaned from drilling waste (dust) by blowing with compressed air or washing with water under pressure.

3.5.5. Driving screws 45 mm long with a manual drill driver Metabo Se 2800.

3.5.6. Leveling screw heads.

3.5.7. Installing plastic fasteners on screws.

3.5.8. Installation in fastenings of metal beacons.

3.5.9. Stretching the cord between the beacons.

Fig.9. Scheme for installing beacons for marking the wall


3.6. Priming the base of the facade with an adhesive primer

3.6.1. Preparation of cement-lime mortar in forced mortar mixer SO-46B.

3.6.2. Sealing of local damages and cracks of the surface of the facade, leveling of individual places with lime-cement mortar.

3.6.3. Preparation of the primer by mixing manual electric mixer ZMR-1350E-2.

3.6.4. Base processing deep penetration primer "Weber.prim contact" to eliminate the leakage of the surface of the walls.

3.6.5. Rust removal and treatment with an anti-corrosion primer for metal parts covered with a thermal insulation system.

3.6.6. The completed work on the priming of the facade must be presented to the representative of the technical supervision of the Customer for inspection, and documenting by signing the Certificate of Inspection of Hidden Works, in accordance with Appendix 3, RD 11-02-2006.

3.7. Installation of steel, galvanized, socle flashing

3.7.1. Drilling holes with a diameter of 8 mm for the support brackets using a manual perforator RH2551 "STURM"

3.7.2. Fastening of support brackets to the slope with fiberglass dowels at a distance of 50 mm from the edge of the slope.

3.7.3. Installation of a plaster screed with a hydraulic tape with a slope from the wall of the building.

3.7.4. Mounting plinth flashing with powder coating according to RAL on the support brackets.

3.7.5. Fastening the ebb with dowel-nails using washers to the wall through a thermal break, inserting them into the prepared hole and knocking them out with a mounting hammer.

3.7.6. Establishment of overlays along the edges of the ebb, preventing the flow of water on the sides of the ebb.

3.7.7. The completed work on the installation of the basement ebb must be presented to the representative of the technical supervision of the Customer for inspection, and documenting by signing the Certificate of Inspection of Critical Structures, in accordance with Appendix 4, RD 11-02-2006.

Fig.10. Scheme of installation of a basement ebb

1 - basement ebb; 2 - base; 3- polyurethane foam; 4 - sealant, sealant; 5 - house wall


3.8. Installation of a steel, galvanized window frame

3.8.1. Drilling holes with a diameter of 8 mm for the support brackets using a manual perforator RH2551 "STURM" . Holes are cleaned from drilling waste (dust) by blowing with compressed air or washing with water under pressure.

3.8.2. Fastening of support brackets to the slope with fiberglass dowels at a distance of 50 mm from the edge of the slope.

3.8.3. Laying a plaster screed with a hydraulic tape with a slope from the wall of the building.

3.8.4. Preliminary measurement of the width and depth of the opening.

3.8.5. Cut the ebb to a certain size using electric jigsaw Bosch PST 900 PEL.

3.8.6. Mounting the tide on the support brackets.

3.8.7. Fixing the tide to the window frame exactly along the edge with a step of 15 cm, with flat-head self-tapping screws using manual drill driver Metabo Se 2800 . Screw the self-tapping screws exactly into the center of the profile without tilting, visually controlling the fit of the corner to the frame, and close the cap with a decorative cap.

3.8.8. Establishment of overlays along the edges of the ebb, preventing the flow of water on the sides of the ebb.

3.8.9. Lubrication of the lower joint of the ebb with the wall with liquid sealant.

3.8.10. The completed work on the installation of window sills must be presented to the representative of the technical supervision of the Customer for inspection and documentation by signing the Certificate of Inspection of Critical Structures, in accordance with Appendix 4, RD 11-02-2006.

Fig.11. Scheme of installation of the ebb with a bracket on a cement screed

1 - casting pad; 2 - window tide; 3 - support bracket; 4 - window box; 5 - galvanized screw; 6 - window sill; 7 - polyurethane foam; 8 - cement mortar; 9 - dowel; 10 - house wall


3.9. Installation of external steel, galvanized side frames of the window unit with powder coating according to RAL

3.9.1. Clearing gaps between installed window block PVC and wall, removal of brown dry mounting foam.

3.9.2. Filling the gaps with acrylic sealant and leveling it with a spatula flush with the slope using foam gun "STANDARD" .

3.9.3. Preliminary measurement of the height (), width () and depth () of the opening.

3.9.4. Cutting sloping corners according to certain sizes (-2 pcs., - 1 pc.) using electric jigsaw Bosch PST 900 PEL .

3.9.5. Drilling holes in the wall of the opening 6 mm, 50 mm, two on top and two on the sides, at an angle and at a distance of 30 mm from the edge of the wall using a manual perforator RH2551 "STURM" .

3.9.6. Driving into the holes of plastic dowels.

3.9.7. Application of mounting adhesive to the reverse side of the sloping corners (panels).

3.9.8. Installation of the upper corner with size B, close to the upper quarter (the narrow shelf of the profile should face the windows, the wide one should face the wall of the opening).

3.9.9. Fastening the upper corner to the wall with dowels, and to the window frame exactly along the edge with a step of 15 cm with flat-head self-tapping screws using manual drill driver Metabo Se 2800 . Screw the screws exactly into the center of the profile without tilting, visually controlling the fit of the corner to the frame, and close the cap with a decorative cap and self-tapping screws.

3.9.10. Filling the gap between the corner and the slope with acrylic sealant, followed by leveling it with a spatula flush with the slope.

3.9.11. Cutting the lower ends of the side corners (panels) at an angle of inclination of the ebb.

3.9.12. By fastening the side corners to the window frame exactly along the edge with a step of 15 cm, using self-tapping screws with a flat head (screw the self-tapping screws exactly into the center of the profile without tilting, visually controlling the tightness of the corner to the frame), close the head with a decorative cap and self-tapping screws to the wall in dowels.

3.9.13. Lubrication of the upper joints of the corners with the wall and the lower joints of the corners with a low tide with liquid sealant.

3.9.14. The completed work on the installation of side window frames must be presented to the Customer's technical supervision representative for inspection and documentation by signing the Certificate of Inspection of Critical Structures, in accordance with Appendix 4, RD 11-02-2006.

Fig.12. Scheme of installation of window frames


3.10. Installation of a basement profile for the installation of insulation

3.10.1. Fixing the aluminum plinth profile AL150 to the base of the facade with dowels at a height of 0.40 m strictly horizontally, ensuring its tight connection to the base of the facade, using special washers of appropriate thickness, leaving a gap between adjacent profiles of 2-3 mm for joining with plastic connecting elements. The distance between the dowels during installation should not exceed 300 mm.

3.10.2. Connecting the base profile with connecting elements. It is forbidden to connect the plinth profile when installing with an overlap.

3.10.3. Installation of compensators for leveling the base profile in the plane. In places where the plinth profile is attached, it is necessary to ensure its tight connection to the base of the facade, using special washers of appropriate thickness.

3.10.4. Formation of a basement profile at the corners of the facade of the building by means of two oblique cuts of the protruding horizontal profile and its subsequent bend.

Fig.13. Installation diagram of the base profile with connecting elements


3.10.5. Stabilization of the profile crate with fiberglass with a width of at least 0.3 m by gluing it to the wall with glue "Weber.therm S 100" with access to the basement profile.

Fig.14. Stabilization of the plinth profile with fiberglass

TYPICAL TECHNOLOGICAL CARD FOR THE INSTALLATION OF A VENTILATED FACADE WITH COMPOSITE PANELS

TK-23

Moscow 2006

The technological map was prepared in accordance with the requirements of the “Guidelines for the development of technological maps in construction”, prepared by the Central Research and Design and Experimental Institute for Organization, Mechanization and Technical Assistance to Construction (TsNIIOMTP), and based on the structures of ventilated facades of NP Stroy LLC.

The technological map was developed for the installation of a ventilated facade using the example constructive system FS-300. The technological map indicates the scope of its application, outlines the main provisions for the organization and technology of work during the installation of elements of a ventilated facade, provides requirements for the quality of work, safety, labor protection and fire prevention measures, determines the need for material and technical resources, calculates labor costs and Work schedule.

The technological map was developed by candidates tech. Sciences V. P. Volodin, YL. Korytov.

1 GENERAL

Hinged ventilated facades are designed for insulation and cladding with aluminum composite panels of external enclosing structures during the construction of new, reconstruction and overhaul of existing buildings and structures.

The main elements of the FS-300 facade system are:

load-bearing frame;

Thermal insulation and wind and hydroprotection;

Cladding panels;

Framing the completion of the facade cladding.

A fragment and elements of the FS-300 facade system are shown in figures , - . Explication to the drawings is given below:

1 - bearing bracket - the main bearing element of the frame, designed for mounting the bearing regulating bracket;

2 - support bracket - an additional element of the frame, designed for fixing the support adjusting bracket;

3 - load-bearing adjusting bracket - the main (together with the load-bearing bracket) load-bearing element of the frame, designed for "fixed" installation of the vertical guide (bearing profile);

4 - support adjusting bracket - an additional (together with the support bracket) frame element designed for movable installation of a vertical guide (bearing profile);

5 - vertical guide - a long profile designed for fastening the cladding panel to the frame;

6 - sliding bracket - fastening element designed to fix the facing panel;

7 - exhaust rivet - a fastener designed to fasten the carrier profile to the carrier adjusting brackets;

8 - set screw - a fastener designed to fix the position of the sliding brackets;

9 - locking screw - a fastener designed for additional fixation of the upper sliding brackets of the panels to the vertical guide profiles in order to avoid shifting of the facing panels in the vertical plane;

Rice. one.Fragment of the facade of the system FS-300

10 - locking bolt (complete with a nut and two washers) - a fastener designed to install the main and additional frame elements in the design position;

11 - thermally insulating gasket of the carrier bracket, designed to level the working surface and eliminate "cold bridges";

12 - thermally insulating gasket of the support bracket, designed to level the working surface and eliminate "cold bridges";

13 - cladding panels - aluminum composite panels assembled with fasteners. They are installed with the help of sliding brackets (6) in the "spacer" and are additionally fixed from the horizontal shift with blind rivets (14) to the vertical guides (5).

Typical dimensions of sheets for the manufacture of cladding panels are 1250×4000 mm, 1500×4050 mm (ALuComp) and 1250×3200 mm (ALUCOBOND). In accordance with the requirements of the customer, it is possible to vary the length and width of the panel, as well as the color of the coating of the front layer;

15 - thermal insulation from mineral wool boards for facade insulation;

16 - wind and hydroprotective material - a vapor-permeable membrane that protects the thermal insulation from moisture and possible weathering of the insulation fibers;

17 - plate dowel for fastening thermal insulation and membrane to the wall of a building or structure.

Facade cladding frames are structural elements designed to decorate a parapet, plinth, window, stained glass and door junctions, etc. These include: perforated profiles for free air access from below (in the basement) and from above, window and door frames, self-bent brackets, flashings, corner plates, etc.

2 SCOPE OF TECHNOLOGICAL SHEET

2.1 A typical flow sheet has been developed for the installation of the FS-300 hinged ventilated facade system for cladding the walls of buildings and structures with aluminum composite panels.

2.2 For the scope of work performed, the facing of the facade of a public building with a height of 30 m and a width of 20 m was taken.

2.3 The scope of work considered by the technological map includes: installation and dismantling of facade lifts, installation of a ventilated facade system.

2.4 Work is performed in two shifts. 2 units of installers work per shift, each on its own vertical grip, 2 people in each unit. Two facade lifts are used.

2.5 When developing a typical flow chart, it was accepted:

walls of the building - reinforced concrete monolithic, flat;

the facade of the building has 35 window openings with the dimensions of each - 1500 × 1500 mm;

panel size: П1-1000×900 mm; П2-1000×700 mm; П3-1000×750 mm; П4-500×750 mm; U1 (corner) - H-1000 mm, V - 350 × 350 × 200 mm;

thermal insulation - mineral wool boards on a synthetic binder 120 mm thick;

air gap between the thermal insulation and the inner wall of the front panel - 40 mm.

When developing a PPR, this typical technological map is tied to the specific conditions of the object with clarification: specifications of the elements of the supporting frame, cladding panels and framing of the facade cladding; thermal insulation thickness; the size of the gap between the heat-insulating layer and the cladding; scope of work; calculation of labor costs; volume of material and technical resources; work schedule.

3 ORGANIZATION AND TECHNOLOGY OF WORK PERFORMANCE

PREPARATORY WORK

3.1 Prior to the start of installation work on the installation of a ventilated facade of the FS-300 system, the following preparatory work must be carried out:

Rice. 2. Scheme of organization of the construction site

1 - fencing of the construction site; 2 - workshop; 3 - material and technical warehouse; 4 - work zone; 5 - the boundary of the zone dangerous for finding people during the operation of facade lifts; 6 - open storage area for building structures and materials; 7 - lighting mast; 8 - facade lift

Inventory mobile buildings are installed at the construction site: an unheated logistics warehouse for storing elements of a ventilated facade (composite sheets or panels ready for installation, insulation, vapor-permeable film, structural elements load-bearing frame) and a workshop - for the manufacture of cladding panels and framing the completion of facade cladding in construction conditions;

They inspect and assess the technical condition of facade lifts, mechanization tools, tools, their completeness and readiness for work;

In accordance with the project for the production of works, facade lifts are installed on the building and put into operation in accordance with the Operation Manual (3851B.00.00.000 RE);

On the wall of the building mark the location of the beacon anchor points for the installation of load-bearing and support brackets.

3.2 Facing composite material is delivered to the construction site, as a rule, in the form of sheets cut to the design dimensions. In this case, in the workshop on the construction site, with the help of hand tools, blind rivets and cassette assembly elements, facing panels are formed with fasteners.

3.3 It is necessary to store sheets of composite material at the construction site on beams up to 10 cm thick laid on a flat place, in 0.5 m increments. The height of the stack of sheets should not exceed 1 m.

Lifting operations with packed sheets of composite material should be performed using textile tape slings (TU 3150-010-16979227) or other slings that prevent injury to the sheets.

Do not store the cladding composite material together with aggressive chemicals.

3.4 In the event that a facing composite material arrives at the construction site in the form of finished facing panels with fastening, they are placed in a pack in pairs, front surfaces to each other so that adjacent pairs are in contact with the rear sides. Packs are placed on wooden linings, with a slight slope from the vertical. The panels are laid in two rows in height.

3.5 The marking of the installation points of the bearing and supporting brackets on the wall of the building is carried out in accordance with the technical documentation for the project for the installation of a ventilated facade.

At the initial stage, the beacon lines for marking the facade are determined - the lower horizontal line of the installation points of the brackets and the two vertical lines extreme along the facade of the building.

The extreme points of the horizontal line are determined using a level and marked with indelible paint. At the two extreme points, using a laser level and a tape measure, all intermediate points for installing the brackets are determined and marked with paint.

With the help of plumb lines lowered from the parapet of the building, vertical lines are determined at the extreme points of the horizontal line.

Using facade lifts, mark with indelible paint the installation points of the bearing and support brackets on the extreme vertical lines.

MAIN WORKS

3.6 When organizing the production of installation work, the area of ​​\u200b\u200bthe facade of the building is divided into vertical grips, within which work is performed by different parts of the installers from the first or second facade lifts (Fig.). The width of the vertical grip is equal to the length of the working deck of the facade lift cradle (4 m), and the length of the vertical grip is equal to the working height of the building. The first and second units of installers working on the 1st facade lift, alternating in shifts, carry out sequential installation work on the 1st, 3rd and 5th vertical grips. The third and fourth units of installers working on the 2nd facade lift, alternating in shifts, carry out sequential installation work on the 2nd and 4th vertical grips. The direction of work is from the basement of the building up to the parapet.

3.7 For the installation of a ventilated facade by one link of workers from two installers, a replaceable grip equal to 4 m 2 of the facade is determined.

3.8 Installation of a ventilated facade starts from the basement of the building on the 1st and 2nd vertical grips simultaneously. Within the vertical grip, installation is carried out in the following technological sequence:

Rice. 3. Scheme of splitting the facade into vertical grips

Legend:

Direction of work

Vertical clamps for the 1st and 2nd units of installers working on the first facade lift

Vertical clamps for the 3rd and 4th sections of installers working on the second facade lift

Part of the building on which the installation of the ventilated facade is completed

Cladding panels:

P1 - 1000 × 900 mm;

P2 - 1000 × 700 mm;

P3 - 1000 × 750 mm;

P4 - 500 × 750 mm;

U1 (corner): H=1000 mm, H=350×350×200 mm

Marking the points of installation of bearing and support brackets on the wall of the building;

Fastening sliding brackets to guide profiles;

Installation of ventilated facade cladding elements to the outer corner of the building.

3.9 Installation of the frame of the facade cladding of the plinth is carried out without using a facade lift from the ground (with a plinth height of up to 1 m). The parapet tide is mounted from the roof of the building at the final stage of each vertical grip.

3.10 The installation points of the bearing and support brackets on the vertical grip are marked using beacon points marked on the extreme horizontal and vertical lines (see), using a tape measure, a level and a dyeing cord.

When marking the anchoring points for the installation of bearing and supporting brackets for the subsequent vertical grip, beacons serve as the points of attachment of the bearing and supporting brackets of the previous vertical grip.

3.11 For fastening to the wall of the bearing and supporting brackets, holes are drilled at the marked points, the diameter and depth corresponding to the anchor dowels, which have been tested for strength for this type of wall fencing.

If a hole is drilled in the wrong place by mistake and a new one needs to be drilled, then the latter must be at least one depth away from the wrong one. drilled hole. If it is impossible to fulfill given condition You can use the method of fastening the brackets shown in Fig. 4.

Holes are cleaned from drilling waste (dust) with compressed air.

Rice. 4. Mounting unit for supporting (supporting) brackets if it is impossible to attach them to the wall at the design drilling points

The dowel is inserted into the prepared hole and knocked out with a mounting hammer.

Thermal insulation pads are placed under the brackets to level the working surface and eliminate "cold bridges".

The brackets are fastened to the wall with screws using an electric drill with adjustable speed and appropriate screwing nozzles.

3.12 The device for thermal insulation and wind protection consists of the following operations:

Hanging on the wall through the slots for the brackets of the insulation boards;

Hanging on the heat-insulating plates of the panels of the wind-hydroprotective membrane with an overlap of 100 mm and their temporary fixing;

Drilling through the insulation and the wind and hydroprotective membrane of holes in the wall for dish-shaped dowels in full according to the project and installing the dowels.

The distance from the dowels to the edges of the heat-insulating plate must be at least 50 mm.

The installation of heat-insulating plates starts from the bottom row, which are installed on the starting perforated profile or plinth and mounted from the bottom up.

The plates are hung in a checkerboard pattern horizontally next to each other in such a way that there are no through gaps between the plates. Permissible size of an unfilled seam - 2 mm.

Additional heat-insulating plates must be securely fixed to the wall surface.

To install additional thermal insulation boards, they must be cut with a hand tool. Breaking the insulation boards is prohibited.

During installation, transportation and storage, thermal insulation boards must be protected from moisture, contamination and mechanical damage.

Before starting the installation of heat-insulating plates, the removable grip on which the work will be carried out must be protected from atmospheric moisture.

3.13 Adjusting carrier and support brackets are attached to the carrier and support brackets, respectively. The position of these brackets is adjusted in such a way as to ensure the vertical alignment of the deviation of the wall irregularities. The brackets are fixed with bolts with special stainless steel washers.

3.14 Fastening to the adjusting brackets of the vertical guide profiles is carried out in the following sequence. The profiles are installed in the grooves of the regulating bearing and support brackets. Then the profiles are fixed with rivets to the bearing brackets. In the supporting adjusting brackets, the profile is installed freely, which ensures its free vertical movement to compensate for temperature deformations.

In the vertical joints of two successive profiles, to compensate for thermal deformations, it is recommended to maintain a gap of 8 to 10 mm.

3.15 When connecting to the plinth, the perforated flashing is fastened with a corner to the vertical guide profiles using blind rivets (Fig.).

3.16 Installation of cladding panels starts from the bottom row and leads from the bottom up (Fig. ).

Sliding brackets (9) are installed on the vertical guide profiles (4). The upper sliding bracket is set to the design position (fixed with the set screw 10), and the lower one - to the intermediate one (9). The panel is put on the upper sliding brackets and by moving the lower sliding brackets it is installed “into the spacer”. The upper sliding brackets of the panel are additionally fixed with self-tapping screws from vertical shift. From the horizontal shift, the panels are also additionally attached to the supporting profile with rivets (11).

3.17 When installing cladding panels at the junction of vertical guides (bearing profiles) (Fig. ), two conditions must be observed: the top cladding panel must close the gap between the bearing profiles; the design value of the gap between the lower and upper facing panels must be exactly maintained. To fulfill the second condition, it is recommended to use a template made of a wooden square bar. The length of the bar is equal to the width of the cladding panel, and the edges are equal to the design value of the gap between the lower and upper cladding panels.

Rice. 5. Junction to the plinth

Rice. 6. Installing the cladding panel

Rice. 7. Installation of cladding panels at the junction of load-bearing profiles

Rice. 8. Mounting unit for cladding panels on the outer corner of the building

3.18 The connection of the ventilated facade to the outer corner of the building is carried out using a corner facing panel (Fig. 8).

Corner cladding panels are manufactured by the supplier-manufacturer or at the construction site with the dimensions specified in the façade design.

The corner cladding panel is attached to the supporting frame by the above methods, and to the side wall of the building - using the corners shown in Fig. 8. A prerequisite is the installation of anchor dowels for fixing the corner cladding panel at a distance of at least 100 mm from the corner of the building.

3.19 Within the interchangeable grip, the installation of a ventilated facade that does not have junctions and window frames is carried out in the following technological sequence:

Marking of anchoring points for the installation of load-bearing and support brackets on the wall of the building;

Drilling holes for installing anchor dowels;

Fastening to the wall of bearing and supporting brackets using anchor dowels;

Thermal insulation and wind protection device;

Fastening to the bearing and supporting brackets of the adjusting brackets with the help of locking bolts;

Fastening to the adjusting brackets of the guide profiles;

Installation work is carried out in accordance with the requirements specified in paragraphs. - and pp. and this technological map.

3.20 Within the interchangeable grip, the installation of a ventilated facade with a window frame is carried out in the following technological sequence:

Marking of anchor points for the installation of load-bearing and support brackets, as well as anchor points for fixing window frame elements on the wall of the building;

Fastening to the wall of the elements of the substructure of the window frame ();

Fastening to the wall of load-bearing and supporting brackets;

Thermal insulation and wind protection device;

Fastening to the bearing and support brackets of the adjusting brackets;

Fastening to the adjusting brackets of the guide profiles;

Fastening the window frame to the guide profiles with additional fastening to the frame profile (Fig. , , );

Installation of facing panels.

3.21 Within the interchangeable grip, the installation of a ventilated facade adjoining the parapet is carried out in the following technological sequence:

Marking of anchoring points for installation of load-bearing and supporting brackets to the wall of the building, as well as anchoring points for attaching the parapet flashing to the parapet;

Drilling holes for installing anchor dowels;

Fastening to the wall of bearing and supporting brackets using anchor dowels;

Thermal insulation and wind protection device;

Fastening to the bearing and supporting brackets of the adjusting brackets with the help of locking bolts;

Fastening to the adjusting brackets of the guide profiles;

Installation of facing panels;

Fastening the parapet tide to the parapet and to the guide profiles ().

3.22 During breaks in work on a replaceable grip, the insulated part of the facade that is not protected from atmospheric precipitation is covered with a protective polyethylene film or in another way to prevent the insulation from getting wet.

4 REQUIREMENTS FOR QUALITY AND ACCEPTANCE OF WORKS

4.1 The quality of the ventilated facade is ensured by the current control of the technological processes of preparatory and installation work, as well as during the acceptance of work. According to the results of the current control of technological processes, certificates of examination of hidden works are drawn up.

4.2 In the process of preparing the installation work, check:

Readiness of the working surface of the facade of the building, structural elements of the facade, means of mechanization and tools for installation work;

Material: galvanized steel (sheet 5 > 0.55 mm) according to GOST 14918-80

Rice. nine. General form window frame

Rice. 10. Adjacent to the window opening (lower)

horizontal section

Rice. 11. Adjacency to the window opening (side)

* Depending on the density of the building envelope material.

Rice. 12. Adjacency to the window opening (upper)

vertical section

Rice. 13. Node junction to the parapet

The quality of the supporting frame elements (dimensions, absence of dents, bends and other defects of brackets, profiles and other elements);

The quality of the insulation (dimensions of the plates, the absence of gaps, dents and other defects);

The quality of the cladding panels (dimensions, absence of scratches, dents, bends, breaks and other defects).

4.3 In the process of installation work, they check for compliance with the project:

Facade marking accuracy;

Diameter, depth and cleanliness of holes for dowels;

Accuracy and strength of fastening of bearing and support brackets;

Correctness and strength of fastening to the wall of insulation boards;

The position of the adjusting brackets that compensate for the unevenness of the wall;

The accuracy of the installation of the supporting profiles and, in particular, the gaps at the points of their joining;

flatness facade panels and air gaps between them and insulation boards;

The correctness of the arrangement of frames for the completion of the ventilated facade.

4.4 When accepting work, the ventilated facade is inspected as a whole and especially carefully the frames of the corners, windows, the basement and the parapet of the building. Defects found during the inspection are eliminated before the facility is put into operation.

4.5 Acceptance of the assembled façade is documented by an act with an assessment of the quality of work. The quality is assessed by the degree of conformity of the parameters and characteristics of the mounted facade specified in the technical documentation for the project. Attached to this act are certificates of examination of hidden works (according to).

4.6 Controlled parameters, methods for their measurement and evaluation are given in Table. one.

Table 1

Controlled parameters

Technological processes and operations

Parameters, characteristics

Tolerance of parameter values

Method of control and tool

Control time

Facade marking

Marking Accuracy

0.3 mm per 1 m

Laser level and level

In the process of marking

Drilling holes for dowels

Depth h, diameter D

Depth h more than the length of the dowel by 10 mm; D+ 0.2 mm

Depth gauge, inside gauge

During drilling

Mounting brackets

Accuracy, strength

According to the project

Level, level

In the process of fastening

Insulation wall mount

Strength, correctness, humidity no more than 10%

moisture meter

During and after fixing

Fixing the adjusting brackets

Compensating for uneven walls

Visually

Fastening guide profiles

Gaps at joints

According to the project (at least 10 mm)

In progress

Fastening of facing panels

Deviation of the facade surface plane from the vertical

1/500 of the height of the ventilated facade, but not more than 100 mm

Measuring, every 30 m along the width of the facade, but at least three measurements per received volume

During and after installation of the facade

5 MATERIAL AND TECHNICAL RESOURCES

5.1 The need for basic materials and products is given in table 2.

table 2

Name

unit of measurement

The need for 600 m 2 of the facade (including the total area of ​​​​windows 78.75 m 2)

Installation of the supporting frame:

carrier bracket

support bracket

load-bearing adjustment bracket

support adjusting bracket

vertical guide

sliding bracket

blind rivet 5×12 mm (stainless steel)

set screw

locking bolt M8 complete with washer and nut

locking screw

window mount bracket

Thermal insulation and wind protection device:

insulation

dowel dowel

windproof film

Installation of facing panels

cladding panel:

П1 - 1000×900 mm

П2 - 1000×700 mm

П3 - 1000×750 mm

П4 - 500×750 mm

U1 - outer corner, H - 1000 mm, IN- 350×350×200 mm

perforated profile (plinth)

framing adjunctions to the window opening:

lower (L - 1500 mm)

side (L = 1500 mm)

top (L = 1500 mm) pcs.

top cladding panel (parapet assembly)

5.2 The need for mechanisms, equipment, tools, inventory and fixtures is given in table 3.


Table 3

Name

Type, brand, GOST, drawing No., manufacturer

Specification

Purpose

Quantity per link

Facade lift (cradle)

PF3851B, CJSC "Tver Experimental Mechanical Plant"

Working platform length 4 m, load capacity 300 kg, lifting height up to 150 m

Production of installation work at height

Plumb, cord

Length 20 m, weight 0.35 kg

Measurement of linear dimensions

Lever-end screwdriver no one

Profi screwdriver INFOTEKS LLC

Reversible lever

Manual impact wrench

The tightening torque is determined by race couple

Screwing/unscrewing nuts, screws, bolts

Electric drill with bits for screwing

Interskol DU-800-ER

Power consumption 800 W, maximum drilling diameter in concrete 20 mm, weight 2.5 kg

Drilling holes and screwing screws

Hand riveting tools

Riveting tongs "ENKOR"

Rivet installation

Battery riveting gun

Battery riveter ERT 130 "RIVETEC"

Rivet force 8200 N, stroke 20 mm, weight with battery 2.2 kg

Installation of blind rivets

Scissors for cutting metal (right, left)

Scissors manual electric VERN-0,52-2,5; metal shears "Master"

Power 520 W, cutting thickness of aluminum sheet up to 2.5 mm; right, left, size 240 mm

Cutting of cladding panels

Dowel driving

Protective gloves for laying thermal insulation

split

Work safety

Fences for inventory areas of work

GOST 2340-78

Location in fact

Safety belt

Construction helmet

GOST 124.087-84

Weight 0.2 kg

8.6 Workplaces, if necessary, must have temporary fences in accordance with the requirements of GOST 12.4.059-89 “SSBT. Construction. Protections are protective inventory. General technical conditions".

8.7 The construction site, work sites, workplaces, driveways and approaches to them at night must be illuminated in accordance with the requirements of GOST 12.1.046-85 “SSBT. Construction. Lighting standards for construction sites. Illumination should be uniform, without blinding effect of lighting devices on workers.

8.8 When installing a ventilated facade using a facade lift, the following requirements must be met:

The area around the projection of the lift on the ground must be fenced. The presence of unauthorized persons in this area during operation, installation and dismantling of the lift is prohibited;

When installing the consoles, it is necessary to fix a poster with the inscription “Attention! Consoles are being installed";

Before attaching the ropes to the consoles, it is necessary to check the reliability of the ropes on the thimble;

The fastening of the ropes to the consoles must be checked after each movement of the console;

Ballast consisting of counterweights, after being installed on the console, must be securely fastened. Spontaneous dropping of ballast must be excluded;

When carrying out work on the lift, posters “Do not remove the ballast” and “Dangerous for the life of workers” must be fixed on the consoles;

The lifting and safety ropes must be securely tensioned with weights. When the lift is in operation, the weights must not touch the ground;

Weights and ballast elements (counterweights) must be marked with their actual weight. The use of bulk weights and counterweights is prohibited;

Work on the lift must be carried out only in helmets;

The entrance to the cradle of the lift and the exit from it must be carried out only from the ground;

When working in the cradle of the lift, the worker must use the safety belt with its fastening to the cradle handrails.

8.9 During the operation of the lift, it is prohibited:

Perform work on the lift at a wind speed of more than 8.3 m/s, during snowfall, rain or fog, as well as at night (in the absence of the necessary lighting);

Use a faulty lift;

Overload the lift;

More than two people on the lift;

Carry out welding work from the lift cradle;

Work without covers of winches and catchers.

8.10 Design development of issues related to ensuring the safety of work considered in this map is not required.



1. The first step in the facade insulation technology is the preparation of the surface of the walls of the facade itself.

For step 1 you will need the following:

  • from a tool (metal brushes, a vacuum cleaner, a scraper, a high-pressure unit with heated water, trowels, graters and semi-graters, trowels, rollers, paint sprayers, slats, rules, plumb lines).
  • from materials (polymer cement and cement-sand mortars grades 100-150, penetrating primer).
  • control methods (visual, measuring - rail, plumb, level).
  • controlled parameters (Surface evenness, absence of cracks, shells. Uniformity of surface priming, conformity of the choice of primer to the type of base). Thickness of layers - in 1 layer no more than 0,5 mm. Drying time - at least 3 hours.

Works of this stage:

  • Mechanical cleaning threw. brushes from dirt and dust. In case of concrete walls removal of smudges of concrete and cement laitance. Leveling surface irregularities, sealing cracks, depressions, sinks, recesses with polymer cement mortar M-100, 150. In the case of repair and restoration work, old (convex) plaster or tiles are removed, the facade is plastered with cement-sand mortar M-100.
  • Priming the surface with a primer.
  • Dilution with water penetrating primer 1:7

2. The second stage is the preparation of the adhesive mass.

For step 2 you will need the following:

  • from material (Glue)
  • from the tool (Container with a volume of at least 10 liters. Mixer, drill and special nozzles, buckets)
  • control method (Visual, laboratory)
  • controlled parameters (dosage of components, compliance of adhesive masses, (uniformity, mobility, adhesive strength, etc.) requirements of technical specifications).

Works of this stage:

  • Open a standard 25 kg bag of dry mix.
  • - In a clean container, the volume of which is at least 10 liters, pour 5 liters of water (from +15 to +20 ° C) and, adding the dry mixture in small portions to the water, mix it with a low-speed drill with a special nozzle until a homogeneous creamy mass is obtained.
  • - After a 5-minute break, mix the finished adhesive mass again.
  • - Preparation of the adhesive mass is carried out at an air temperature of +5°C and above.

3. The third stage is the installation of the first row of insulation using a basement profile

For step 3 you will need the following:

  • from the material (basement profile, anchors, mineral wool insulation
  • glue metal nails, bolts, dowels)
  • from a tool (Electric wrenches, hammers, plumb lines, theodolite - level, knives, metal rulers, serrated and smooth spatulas, a device for cutting plates, hammers, tape measures, plumb lines, theodolite - level)
  • control method (Visual, measuring optical (by level))
  • controlled parameters (Design position, horizontal fastening, layer thickness in accordance with the Technical Certificate). Thickness of a layer - 10-15 mm., Drying time - days.

Works of this stage:

  • Set the base profile horizontal to zero.
  • The profile should be fastened with anchors or dowels in accordance with the Technical Certificate.
  • Alignment of the wall to produce special plastic gaskets.
  • The profile is connected using special gaskets that are part of the system.
  • Cut mineral wool boards (insulation) into strips of 300 mm to install the first row of insulation.
  • Apply the adhesive mass with a notched trowel in a continuous layer on a strip of mineral wool board.
  • Glue the insulation to the wall.
  • After 48-72 hours, drill a hole in the wall for the dowel through the insulation strip and install it (the distance from the edge of the strip to the dowel is 100 mm, and between the dowels is not more than 300 mm).
  • Caulk the seams between the strips of mineral wool boards with scraps of insulation

4. Installation of a standard range of insulation from PSB-S-25F

For step 4 you will need the following:

  • from material (Glue "Thermomax 100K", insulation, PSB-S-25F, dowel, metal nails)
  • from the tool (See above, Grinding stones, with a pressure device)
  • controlled parameters (design position, thickness of the adhesive layer, absence of gaps of more than two mm between the insulation boards, gear ligation, adhesive strength of the adhesive layer to the base surface and to the surface of the insulation, the number of dowels per 1 sq.m, the fixation strength of the dowels, the depth .). Layer thickness - 10-15 mm. Drying time - 1 day.

Works of this stage:

  • Apply the adhesive mass on the PSB-S-25F slab in one of three ways, which are indicated in the instructions for use, depending on the curvature of the walls.
  • Glue the PSB-S25F slab to the wall (with dressing for ½ of the slab relative to the bottom row of insulation).
  • After 48-72 hours, drill a hole in the wall for the dowel through the PSB-S-25F slab and install it depending on the number of storeys of the building and the type of foundation.
  • Caulk the seams between the insulation boards with insulation scraps.
  • Make sanding of the installed plates PSB-S-25

Stage 4.1: Installation of cuts from a mineral wool board between floors

For step 4.1 you will need the following:

  • from the tool (Tapes, plumb lines, level, knives, metal rulers, notched and smooth spatulas, electric wrenches, hammers, tape measures)
  • method of control (Visual, measuring, input control of materials)

Works of this stage:

  • Cut the mineral wool board into 200mm strips.
  • Apply the adhesive mass to the entire plane of the insulation strip with a notched trowel.
  • Glue the insulation to the wall at the level of the upper slope of the window of each floor with a continuous strip.
  • After 48-72 hours, drill a hole in the wall for the dowel through the strip of insulation and install it (the number of dowels is 3 pieces per strip, the distance from the edge of the strip to the dowel is 100 mm and between the dowels is no more than 300 mm).
  • Finish off the metal nails in the dowels.
  • To caulk the seams between the PSB-S-25F mineral wool boards with scraps of insulation.

Stage 4.2: Installation of a standard range of mineral wool insulation

For step 4.2 you will need the following:

  • from the material (Insulation mineral wool board, glue, dowel, metal nails, bolts)
  • from the tool (Tapes, plumb lines, level, knives, metal rulers, notched and smooth spatulas, electric wrenches, hammers, tape measures)
  • control method (Visual, measuring)
  • controlled parameters (design position, horizontal fastening, thickness and cohesion of the adhesive layer in accordance with the normative and technical documentation and this map). Layer thickness - 10-15 mm. Drying time - 1 day.

Works of this stage:

  • Apply the adhesive mass to the mineral wool board in one of the three ways indicated in the instructions, depending on the unevenness of the walls.
  • Glue the mineral wool slab to the wall (with ligation of the slabs relative to the lower row of insulation).
  • After 48-72 hours, drill a hole in the wall for the dowel through the insulation plate and install it, depending on the number of storeys of the building and the type of foundation.
  • Finish off metal nails or bolts in dowels.

Stage 5 Installation of fire breaks around window and door openings.

For step 5 you will need the following:

  • from the material (Insulation mineral wool board, glue, dowel, metal nails)
  • from a tool (Metal rulers, notched and smooth spatulas, a tool for cutting insulation boards)
  • method of control (Visual, measuring, input control of materials)
  • controlled parameters (design position, continuity and thickness of the adhesive layer, the width of the cuts, the absence of gaps of more than two mm between the insulation plates, the installation scheme of the insulation at the tops of the corners of the openings (“boots”), the number of dowels, the anchoring depth of the dowel in the base, the strength of fixation in the base) . Layer thickness - 10-15 mm. Drying time - 1 day.

Works of this stage:

  • Cut the insulation into strips with a width equal to or more than 150 mm
  • Apply the adhesive mass in a continuous layer on a strip of mineral wool board with a notched trowel.
  • Install strips of mineral wool board around the perimeter of the window according to the typical system assembly.
  • After 48-72 hours, drill a hole in the wall through the strips of mineral wool board under the dowel and install it (the number of dowels is 3 pcs per one strip, the distance from the edge of the strip to the dowel is 100mm and between the dowels is no more than 300mm).
  • Finish off the metal nails in the dowels.
  • Caulk the seams between the plates and trimmings of the insulation

Stage 6 Reinforcement of building corners, window and door openings

For step 6 you will need the following:

  • material (Universal elastic compound, plastic corner)
  • from a tool (Metal rulers, notched and smooth spatulas, a tool for cutting plates and insulation)
  • method of control (Visual, measuring, input control of materials)
  • controlled parameters ( Appearance, straightness of the surface). Layer thickness - 3-5 mm. Drying time - 1 day.

Works of this stage:

  • Install a plastic corner on the insulation at the corners of the building, window and door openings.

Stage 7. Application of a reinforcing layer on window and door slopes

For step 7 you will need the following:

  • material (universal elastic mixture, reinforcing mesh)
  • from a tool (Spatulas, trowels, brushes, trowels, a grinding bar with a pressure device, rule rails)
  • method of control (Visual, measuring, input control of materials)
  • controlled parameters (appearance, availability of additional mesh layers). Layer thickness - 3-5 mm. Drying time - 1 day.

Works of this stage:

  • Apply the mixture to the end and outer plane of the mineral wool board.
  • Drown the previously glued corner reinforcing mesh into the freshly applied mixture.
  • Remove excess mixture
  • After the first layer has dried, glue additional strips of diagonal reinforcing mesh (kerchiefs) at the corners of window, door and other openings

Stage 8. Installation of an anti-vandal base layer for the first floors of a building

For step 8 you will need the following:

  • made of material (universal elastic mixture, shell mesh)
  • method of control (Visual, measuring, input control of materials)
  • controlled parameters (total thickness of the reinforcing layer in accordance with the technical certificate, the width of the overlap, the presence of additional diagonal overlays at the tops of the corners of the openings). Layer thickness - 3 mm. Drying time - 1 day.

Works of this stage:

  • Drown the armored mesh without gaps in the freshly laid mixture. The connection of the panzer mesh web is mounted end-to-end, without overlap.
  • Remove excess mixture

Stage 9 Applying a reinforcing layer on the plane of the insulation

For step 9 you will need the following:

  • from material (Universal elastic mixture, ordinary reinforcing mesh)
  • from a tool (Spatulas, brushes, trowels, trowels, a grinding bar with a pressure device, rule rails)
  • method of control (Visual, measuring, input control of materials)
  • controlled parameters (Total thickness of the reinforcing layer in accordance with the Technical Certificate, overlap width, the presence of additional diagonal linings at the tops of the corners of the openings). Layer thickness - 4 mm. Drying time - 1 day.

Works of this stage:

  • Apply the mixture to the plane of the insulation boards.
  • Drown into the freshly laid adhesive mass an ordinary reinforcing mesh without gaps, with an overlap of sheets of at least 100 mm at vertical and horizontal joints.
  • Remove excess adhesive mass.
  • Apply adhesive mass for leveling on the dried surface of the reinforcing layer, completely covering the reinforcing mesh and creating a smooth surface.
  • After the leveling layer has dried, smooth out the irregularities with sandpaper.

10 stage. Primer for decorative finishing

For step 10 you will need the following:

  • from material (Quartz primer)
  • from a tool (roller, spray guns, compressor, paint gun)
  • control method (Visual)
  • controlled parameters (primer uniformity, primer conformity). Layer thickness - 0.5 mm. Drying time - at least 3 hours.

Works of this stage:

  • Prepare the primer composition for work.
  • Dust off the plastered surface.
  • Apply the primer manually by roller or mechanically over the entire surface without gaps in one coat.

Stage 11: Applying decorative plaster

For step 11 you will need the following:

  • from material (decorative mixture)
  • from a tool (Stainless steel grater, plastic grater)
  • control method (Visual)
  • controlled parameters (no transitions, uniform smoothing, crumb). Layer thickness - 2.5-3 mm. Drying time - 7 days.

Works of this stage:

  • Preparation of mortar mixture. (see item 2).
  • Applying plaster.

Stage 11.1: Painting the decorative protective layer

For step 11.1 you will need the following:

  • material (Paint)
  • from the tool (Rollers, paint installations)
  • control method (Visual)
  • controlled parameters (Uniformity of color, uniformity, docking of sections). Layer thickness - 2 layers no more than 0.5 mm. Drying time - 5 hours.

Works of this stage:

Prepare the paint composition for work.

Apply the paint composition manually with a roller or mechanically, twice covering the entire primed surface.

Stage 12: Sealing the joints between the insulation system and the building structure

For step 12 you will need the following:

  • of material (sealing cord, sealant)
  • from the tool (Spatulas, sealant gun)
  • control method (Visual)
  • controlled parameters (no cracks, coating thickness)

Works of this stage:

  • The gaps between the insulation system and the building structure are filled sealing cord along the entire length of the joint, and sealed with polyurethane sealant.